Façade Schedule

ST & NT Façade Work Schedule

NORTH TOWER
*NO WORK 10/19 or 10/20*

WORK WEEK 10/05-10/09 FLR 13 10/2-10/07
FLR 12 10/2-10/07
FLR 11 10/05-10/08
FLR 10 10/05-10/08
FLR 9 10/06-10/09
FLR 8 10/06-10/09
FLR 7 10/07-10/12
FLR 6 10/07-10/12
FLR 5 10/08-10/13
FLR 4 10/08-10/13
FLR 3 10/09-10/14
FLR 2 10/09-10/14
FLR 1 10/09-10/14

WORK WEEK 10/12-10/16 FLR 35 10/13-10/16
FLR 34 10/13-10/16
FLR 33 10/14-10/21
FLR 32 10/14-10/21
FLR 31 10/15-10/22
FLR 30 10/15-10/22
FLR 29 10/16-10/23
FLR 28 10/16-10/23

 

SOUTH TOWER

WORK WEEK 10/05-10/09 FLR 18 10/02-10/07
FLR 17 10/02-10/07
FLR 16 10/05-10/08
FLR 15 10/05-10/08
FLR 14 10/06-10/09
FLR 13 10/06-10/09
FLR 12 10/07-10/12
FLR 11 10/07-10/12
FLR 10 10/08-10/13
FLR 9 10/08-10/13
FLR 8 10/09-10/14
FLR 7 10/09-10/14

WORK WEEK 10/12-10/16 FLR 6 10/12-10/15
FLR 5 10/12-10/15
PARAPET 10/13-10/16
FLR 22 10/15-10/20
FLR 21 10/15-10/20
FLR 20 10/16-10/21
FLR 19 10/16-10/21